Western Corridor Recycled Water Project- Gibson Island
Patricks Terminal - Brisbane
Western Corridor Recycled Water Project
MRTT HANGAR AMBERLEY
MRTT HANGAR AMBERLEY
MRTT HANGAR AMBERLEY
AUSTRALIA ZOO
BRISBANE BMW
PORCHE BRISBANE
DFO BRISBANE
CURRAGH NORTH
CARLTON UNITED BREWERIES WAREHOUSE
Woolworths
Patricks Terminal - Brisbane Patricks Terminal - Brisbane
Patricks Terminal - Brisbane Patricks Terminal - Brisbane
Patricks Terminal - Brisbane Patricks Terminal - Brisbane
Patricks Terminal - Brisbane Patricks Terminal - Brisbane
Patricks Terminal - Brisbane Patricks Terminal - Brisbane
Patricks Terminal - Brisbane Patricks Terminal - Brisbane
JOB: Supply & Erect Structural Steel Buildings
CLIENT: Patricks Terminals 10 Extension - Grindley Constructions PTY LTD
TONNAGE: 635 Ton
DATE PROJECT COMMENCED: January 2008
DURATION OF SCOPE: 12 Months
SPECIFICATION:
Welding: AS 1554.1 SP
Fabrication: AS 4100
Purlins: Stramit Zam- 15 yr guarantee
Protective Coating:
System 1: Abrasive Blast to AS 1627.4 Class 2 ½ One coat Interzinc 215 min 75 microns DFT
System 2: Abrasive Blast to AS 1627.4 Class 2 ½
First Coat: Interzinc 215 75 microns DFT
Second Coat: Intergard 475HS 200 microns DFT
Third Coat: Interthane 870 75 microns DFT
System 3: Hot Dipped Galvanised to AS/NZS 4680-2006 with a 15 year Guarantee
DESCRIPTION:

Supply, fabrication and installation of 1 Control Tower, 1 Administration Building, 1 substation, 1 Pump station, 1 Workshop and 1 Store.